OK, looking back I see that we had a plan to finish first fix by January. It is now the end of February and we are still plodding forward. :-(  Still things are actually moving so it isn't that bad - and you can see we have made quite a bit of progress. They started by putting up plasterboard onto the walls.

 

the steel beams get boxed in so they can be plaster boarded as well

 

The lounge roof section was completed

They then moved on into the other rooms

And put door linings around the holes in the walls.

 

 I had got the window sills machined and glued up ready to be installed.
These things are solid oak and 18 inches (50cm) deep and over 1 inch (3cm) thick.

 

Once fitted and fixed in, the sills are protected before the plasterers come back.

So now the plaster boarding will finish in the next few days and they can then start putting on a plaster skim coat. Once this is done and dried, we will be ready for the second fix.