Well it was October 22nd when the original builder left the site. This was only 5 months late - and he still hadn't completed the job. The 'revised' plan had been for him to get the rafters on and to purchase the cladding and then the 2nd builder would take over to finish the work. At least that was the plan. When they left it looked like this.
When the new roofer came on site he found that all of the original work was done so badly that it mostly had to be stripped off and reinstalled. This took 4 weeks and meant that we would not be in the house by Christmas :-(
The first problem they found was that when they tried to lay external cladding onto the rafters they would not lay flat as the rafters were not even in line.
Here is an example of the fine work done. These rafters don't actually go anywhere.
This dormers were unsupported and unfinished.
The rafters on the left were all stripped off and reset. Now they fit against the steel support and are fixed properly into the wall.

All of these trusses were hand cut - wrongly. When checked it was found that the roof ridge was not parallel to the wall. Each rafter had to be taken off, turned round and recut by hand.

The problems didn't stop there. When the windows arrived, they didn't fit.

Considering that the house is supposed to air tight, this is quite a big gap.

Finally the roof was in line, square and properly fixed down. It was time to clad and insulate the outside.
At the same time we started to try and do some external landscaping. Unfortunately the digger driver decided that we needed to finish the driveway and entrance and so this is on hold.
Still, we now have an entrance to receive deliveries.